This bill aims to improve the efficiency and reliability of California's electrical grid. The Public Utilities Commission (PUC) will establish energy targets and timelines for public utilities, and impose penalties on companies that fail to meet these targets. The PUC will also designate areas as "infrastructure-constrained energization areas" and adopt rules for over-the-fence transactions in these areas. These areas will be characterized by limited distribution or transmission infrastructure, inland or desert geography, and extended energy timelines. To address the challenges in these areas, the bill will facilitate the development of electrical generation and energy storage facilities, and expedite permitting and construction of electrical infrastructure. The Independent System Operator (ISO) will prioritize projects in these areas, and the PUC and ISO will work together to streamlin…
| Mar. 09, 2026 | Referred to Coms. on U. & E. and NAT. RES. |
| Feb. 20, 2026 | From printer. May be heard in committee March 22. |
| Feb. 19, 2026 | Read first time. To print. |
| Introduced by Assembly Member Carrillo |
February 19, 2026 |
LEGISLATIVE COUNSEL'S DIGEST
The people of the State of California do enact as follows:
SECTION 1.
(a) The Legislature finds and declares all of the following:SEC. 2.
Section 21080.74 is added to the Public Resources Code, to read:21080.74.
(a) This division does not apply to the approval of an electrical generation or energy storage project located within an infrastructure-constrained energization area if all of the following conditions are met:SEC. 3.
Section 348.5 is added to the Public Utilities Code, to read:348.5.
(a) The Independent System Operator shall, consistent with federal law and its federally approved tariff, consider regional economic development needs, infrastructure constraints, and statewide policy objectives when conducting transmission planning and interconnection processes.SEC. 4.
Section 367.8 is added to the Public Utilities Code, to read:367.8.
(a) The commission shall designate an infrastructure-constrained energization area based on objective criteria, including, but not limited to, limited distribution or transmission infrastructure relative to available electrical capacity or projected load growth, inland or desert geography, and extended energization timelines.SEC. 5.
Section 934.5 is added to the Public Utilities Code, to read:934.5.
(a) The commission shall require each electrical corporation to meet energization timelines or targets established pursuant to this article or by commission order.SEC. 6.
No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act or because costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIII B of the California Constitution.