AB 2383: Electricity: data centers.
<p>The bill requires the California Public Utilities Commission to create a separate rate classification for large energy use facilities by January 1, 2028. This new classification must have its own distinct rate schedule and meet specific requirements. The commission must also ensure that any proposed rate schedules comply with certain criteria before approving them. Additionally, load-serving entities providing electricity to these facilities must enter into contracts covering the cost of service and energizing costs by January 1, 2027. These contracts are subject to specified conditions. Violations of this act or commission actions implementing it would be considered a crime.</p>
- What is the current status of AB 2383?
- As of September 23, 2026, AB 2383 is recorded as "Chaptered/Signed": it has been signed by the Governor and chaptered into law. The last recorded action, on September 21, 2026, was "Chaptered by Secretary of State - Chapter 435, Statutes of 2026".
- Did AB 2383 pass?
- Yes. AB 2383 passed both houses and was signed into law (last action September 21, 2026). Most California bills signed in a given year take effect on January 1 of the following year, unless the bill carries an urgency clause or sets its own operative date.
- Who wrote AB 2383, and where is it now?
- AB 2383 was authored by Asm. Rick Chavez Zbur with 2 coauthors. It is filed under Public Utilities, alongside 149 other California Public Utilities bills this session.
LEGISLATIVE COUNSEL'S DIGEST
The people of the State of California do enact as follows:
SECTION 1.
Section 945.1 is added to the Public Utilities Code, to read:945.1.
For purposes of this article, all of the following definitions apply:SEC. 2.
Section 945.4 is added to the Public Utilities Code, to read:945.4.
As part of a new or existing proceeding, the commission shall require each electrical corporation to file a transmission and distribution service tariff that does at least both of the following, to the extent permitted by federal law:SEC. 3.
Section 945.5 is added to the Public Utilities Code, to read:945.5.
(a) As part of a new or existing proceeding the commission shall require each electrical corporation to file a generation service tariff that does at least all of the following:SEC. 4.
Section 945.6 is added to the Public Utilities Code, to read:945.6.
(a) (1) On or before January 1, 2028, each community choice aggregator, consistent with Section 366.2, or electric service provider, consistent with Section 394, shall adopt a tariff for generation service for data centers.SEC. 5.
Section 945.8 is added to the Public Utilities Code, to read:945.8.
(a) This article does not expand the amount of retail load eligible to participate in direct access transactions pursuant to Section 365.1.SEC. 6.
No reimbursement is required by this act pursuant to Section 6 of Article XIII B of the California Constitution because a local agency or school district has the authority to levy service charges, fees, or assessments sufficient to pay for the program or level of service mandated by this act or because costs that may be incurred by a local agency or school district will be incurred because this act creates a new crime or infraction, eliminates a crime or infraction, or changes the penalty for a crime or infraction, within the meaning of Section 17556 of the Government Code, or changes the definition of a crime within the meaning of Section 6 of Article XIII B of the California Constitution.| Sep. 21, 2026 | Chaptered by Secretary of State - Chapter 435, Statutes of 2026. |
| Sep. 21, 2026 | Approved by the Governor. |
| Sep. 15, 2026 | Enrolled and presented to the Governor at 3 p.m. |
| Aug. 31, 2026 | Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 67. Noes 2.). |
| Aug. 31, 2026 | Assembly Rule 63 suspended. |