Senate BillChaptered/SignedPublic Contract

SB 598: Public contracts: local water infrastructure projects: Construction Manager/General Contractor project delivery method.

California · Senate · 2025–2026 Regular Session · last verified December 13, 2025

What SB 598 does, verified December 13, 2025

This bill authorizes local agencies to use a construction manager/general contractor project delivery method for regional recycled water projects or other water infrastructure projects. The method allows for a construction manager to provide preconstruction and construction services, and the contract can be entered into at the same time or later. The bill requires local agencies to award contracts on a best value basis or to the lowest responsible bidder and limits the authorization to 15 capital outlay projects per agency. The bill makes the provisions effective until January 1, 2031, and does not require reimbursement for certain costs.

Bill journey
IntroducedComplete
In CommitteeComplete
First Chamber FloorComplete
Second ChamberComplete
GovernorComplete
6ChapteredCurrent
Last action: Chaptered by Secretary of State. Chapter 655, Statutes of 2025. (2025-08-29)Alert me
Recent actions28 total · showing 5
Oct. 11, 2025Chaptered by Secretary of State. Chapter 655, Statutes of 2025.
Oct. 11, 2025Approved by the Governor.
Sep. 05, 2025Enrolled and presented to the Governor at 2 p.m.
Aug. 29, 2025Assembly amendments concurred in. (Ayes 37. Noes 0. Page 2287.) Ordered to engrossing and enrolling.
Aug. 29, 2025Assembly amendments concurred in. (Ayes 37. Noes 0.) Ordered to engrossing and enrolling.
Full action history, 23 earlier actionsConnect Plus